Once the bearing structure has been realized, in order to improve insulation inside the rooms, proceed with the following phases:
installation of an insulated and ventilated panel
made of shaped foamed polystyrene with
supports to create channels of ventilation,
coupled with a multi-layered wooden board;
installation of a sheath to be laid parallel to the
gutter line.
laying of roof tiles as described further on.
RECOMMENDATION
Keep the square at a strict 90° angle with the gutter line (FIG.1)
In the event of the pitch deviating from the perpendicular, follow the line parallel to the gutter (FIG.2)
LAYING OF ROOFTILES
Lay and slot in the tiles following the progressive sequence of numbers until the whole pitch is covered.
Lay the first row of tiles at a distance of 10÷15cm overhang and screw them on using the special screws "A".
Attach the tiles inserting and screwing up the "B" screws after which overlap them by means of the coupling mechanism "C".
LAYING OF THE RIDGE
Slot in the brackets using the attachment "A" and position them at a distance which respects the width of the ridge.
Slot in the ridge using the coupling system "B", lay it on the
two rows of brackets and then fasten it all to the highest point of the hollow tile. Fasten down the various modular units of the ridge starting from one end and continuing until the ridge has been completed.